MPC > MPC Bond > Pages > CurrentProjects.aspx
|
Current Projects
|
|
|
|
|
|
MPC > MPC Bond > Current Projects
 |
Fitness Building - Building 24 (4)
Facilities Building (5)
PROJECTS IN PROCESS
Old Library Renovation (6)
- Includes renovation of the former Library building and provides space for campus administration, along with improved access for the disabled.
- Construction began December 2007 and is anticipated to be completed in January 2009.
Infrastructure
- Engineering efforts are under way for a campus-wide rebuilding of site utilities including gas, electricity, water, sewer and storm drains, and data/telephone service.
- Engineering design will be used to identify specifications, budgets, timelines and contracts for future utility work to be performed.
FUTURE PROJECTS
Math/Science Project
- New math classrooms, two math computer labs, a multimedia lab, faculty and staff offices, conference room, testing area, storage and other teaching support space.
- Renovation of Life Sciences and Physical Sciences buildings will include lab space expansion for biology, physics and chemistry; Lecture Forum renovation; modernization of space for other academic programs; and new utility infrastructure and distribution systems.
- The Final Project Proposal was submitted to the Chancellor’s Office on May 31, 2005.
Music/Theater Performing Arts Center
- The new facility will include: 300-seat recital hall performance space, a rehearsal room, practice rooms, music labs, offices and support space.
- Renovation of the Theater facility will provide: new building systems, fire and life safety equipment, new floors, wall and ceiling finishes, a new stage floor, new lighting system, rigging equipment and orchestra pit lift.
- The Initial Project Proposal was submitted to the Chancellor’s Office on May 31, 2005.
|
|
|
|
 |
 |
 |
 |
|